Proposed updates coming to Frye - January 2024

    • Foster Space to replication activities and programming such as the ASU Innovation Center
    • MakerSpace/STEM opportunities for student collaboration and Problem-based Learning (PBL)

    January 2024 Update: Photo album below. Click here for PDF presentation.

Timeline

  • Frye Elementary School DURATION START DATE END DATE
    Master Plan and Phase Schematic Design  10 WEEKS Oct. 3, 2023 Nov. 29, 2023
    Tour of WGA Makerspace   Oct. 3, 2023
    Actual: 10/9
    In-Person Complete
    Meeting 1 - Tour of School | Review Immediate Needs | Develop Program | Discuss Future Needs   Oct. 4, 2023
    Actual: 10/10
    In-Person Complete
    Meeting 2 - Review Future Space Needs Program, Discuss Initial Concept    Oct. 18, 2023
    Actual: 10/25
    In-Person Complete
    Meeting 3 - Review Concepts   Nov. 1, 2023
    Actual: 11/9 
    Virtual Complete
    Meeting 4 - Review Concepts & Phasing Recommendations   Nov. 15, 2023
    Actual: 11/29 
    Virtual Complete
    Meeting 5 - Review Finalized Report   Dec. 12, 2023
    Actual: 12/13
    Virtual Complete
    CONSTRUCTION DOCUMENTS 6 WEEKS    
    Library and Collaboration Phase I -  Summer Improvements   Dec. 13, 2023 Feb. 16, 2024
    Meeting 6 - Review Interior Items finishes, power, data & furniture   Jan. 16, 2024
    To be Confirmed 
     
    Meeting 7 - Furniture   Feb. 7, 2024  
    Furniture Order DUE DATE     To Be Confirmed 
    JOC GMP 4 WEEKS Feb. 16, 2024 Mar. 8, 2024
    Spring Break   Mar. 11, 2024 Mar 16,2024
    CONSTRUCTION ADMINISTRATION
    Concord will provide a detailed schedule
    18 WEEKS TBC TBC
    Subcontracts, Submittals      
    Punch Walk     Jun. 25, 2024
    Substantial Completion      Jul. 2, 2024
    Final Completion     Jul. 10, 2024
    First Day of School     Jul. 17, 2024