Proposed updates coming to Frye - January 2024
-
- Foster Space to replication activities and programming such as the ASU Innovation Center
- MakerSpace/STEM opportunities for student collaboration and Problem-based Learning (PBL)
January 2024 Update: Photo album below. Click here for PDF presentation.
Timeline
-
Frye Elementary School DURATION START DATE END DATE Master Plan and Phase Schematic Design 10 WEEKS Oct. 3, 2023 Nov. 29, 2023 Tour of WGA Makerspace Oct. 3, 2023
Actual: 10/9In-Person Complete Meeting 1 - Tour of School | Review Immediate Needs | Develop Program | Discuss Future Needs Oct. 4, 2023
Actual: 10/10In-Person Complete Meeting 2 - Review Future Space Needs Program, Discuss Initial Concept Oct. 18, 2023
Actual: 10/25In-Person Complete Meeting 3 - Review Concepts Nov. 1, 2023
Actual: 11/9Virtual Complete Meeting 4 - Review Concepts & Phasing Recommendations Nov. 15, 2023
Actual: 11/29Virtual Complete Meeting 5 - Review Finalized Report Dec. 12, 2023
Actual: 12/13Virtual Complete CONSTRUCTION DOCUMENTS 6 WEEKS Library and Collaboration Phase I - Summer Improvements Dec. 13, 2023 Feb. 16, 2024 Meeting 6 - Review Interior Items finishes, power, data & furniture Jan. 16, 2024
To be ConfirmedMeeting 7 - Furniture Feb. 7, 2024 Furniture Order DUE DATE To Be Confirmed JOC GMP 4 WEEKS Feb. 16, 2024 Mar. 8, 2024 Spring Break Mar. 11, 2024 Mar 16,2024 CONSTRUCTION ADMINISTRATION
Concord will provide a detailed schedule18 WEEKS TBC TBC Subcontracts, Submittals Punch Walk Jun. 25, 2024 Substantial Completion Jul. 2, 2024 Final Completion Jul. 10, 2024 First Day of School Jul. 17, 2024