Proposed Updates Coming to Hull
-
- Re-imagine Media Center to foster increased STEM/Collaboration
- Media & Tech work collaboratively to build 4th-6th Enrichment opportunities with STEM and Research
- Working with CTE to investigate Cyber Security at the elementary level.
- Removing wall between 2 classrooms to build collaborative Spacing for grade levels to work together.
January 2024 Update: Photo album below. Click here for PDF presentation.
- Re-imagine Media Center to foster increased STEM/Collaboration
– / 6
Timeline
-
Hull Elementary School DURATION START DATE END DATE Master Plan and Phase I Schematic Design 10 WEEKS Oct. 3, 2023 Nov. 29, 2023 Tour of WGA Makerspace Oct. 3, 2023
Actual: 10/9In-Person Complete Meeting 1 - Tour of School | Review Immediate Needs | Develop Program | Discuss Future Needs Oct. 4, 2023 In-Person Complete Meeting 2 - Review Future Space Needs Program, Discuss Initial Concept Oct. 18, 2023
Actual: 10/25In-Person Complete Meeting 3 - Review Concepts Nov. 1, 2023
Actual: 11/8Virtual Complete Meeting 4 - Review Concepts & Phasing Recommendations Nov. 15, 2023
Actual: 11/29Virtual Complete Meeting 5 - Review Finalized Report Dec. 12, 2023
Actual: 12/13Virtual Complete CONSTRUCTION DOCUMENTS 6 WEEKS Library and Collaboration Phase I - Summer Improvements Dec. 13, 2023
Actual: 1/3/24Feb. 16, 2024 Meeting 6 - Review Interior Items finishes, power, data & furniture Jan. 22, 2024
3:30 pmIn Person with Furniture Vendor Meeting 7 - Furniture Feb. 7, 2024 Furniture Order DUE DATE To Be Confirmed JOC GMP 4 WEEKS Feb. 16, 2024 Mar. 8, 2024 Spring Break Mar. 11, 2024 Mar 16,2024 CONSTRUCTION ADMINISTRATION
Concord will provide a detailed schedule18 WEEKS TBC TBC Subcontracts, Submittals Punch Walk Jun. 25, 2024 Substantial Completion Jul. 2, 2024 Final Completion Jul. 10, 2024 First Day of School Jul. 17, 2024